Hunt for clues in deadly Brooklyn building collapse will take time
Trending
NEW YORK (AP) -- Investigators began what could be a long search for the cause of a Brooklyn apartment building collapse that killed eight people while crews kept removing piles of rubble Thursday in the search for more victims.
The three-story building gave way while construction workers were digging Wednesday afternoon at an adjacent lot, causing New York City’s mayor to order inspections at about 100 building sites involving companies related to the project.
“If there is anyone, or any entity, operating in this city that bears responsibility for what happened, we will hold them fully accountable,” Mayor Zohran Mamdani said during a news conference.
Investigators have not determined what caused the collapse. Two children were among those killed and 18 others were injured, including four firefighters, Mamdani said.
One witness said he watched bricks fall minutes before the disaster while a woman in a neighboring building said she and fellow residents blamed vibrations from the construction for cracks that appeared in their apartment walls.
Emergency workers used power saws and pickaxes to get through the debris, pulling four victims out of the rubble in the early hours of Thursday. Hours later, excavators removed larger chunks of the wreckage so searchers could get deeper into the construction pit, said New York Fire Commissioner Lillian Bonsignore.
“We always assume there are more people there until we can access the ground,” Bonsignore said. “So until we remove some of the bigger debris and are able to search beneath them, this will remain a rescue operation.”
James Williams, who works at a deli across the street, said he heard loud banging at the site all day Wednesday and looked outside to see bricks falling. “Two minutes later, the building collapsed,” he said.
As the building crumbled and exposed the neighboring building, Williams spotted a woman on a staircase. “There wasn’t anything I could do,” he said, his voice cracking.
Customers and stylists at a nearby hair salon jumped up and ran onto the sidewalk as the building fell.
“We heard the boom and we all rushed outside and saw smoke and dust everywhere,” said hairstylist Brigitte Anama.
She saw emergency workers pulling people from the rubble, including what appeared to be a child. “People were saying, ‘Pray for the baby, pray for the baby,'” Anama said.
Dervie Mapp, who lives along the construction site, said she and others complained for months about the project. Her landlord brought engineers into the building, but residents never received an inspection report, she said.
Construction safety expert Glenn Corbett of John Jay College in New York said it’s way too early to know what caused the accident.
“It could be a design flaw, it could be a construction flaw, or it could be some kind of work that was going on,” he said.
It appeared that the shoring of the excavation work failed, but finding out why will take more investigating, he said.
The one-story building previously on the site was demolished earlier this year. Records show a contractor, Mordechai “Marty” Waisbrod, notified the city that excavation would begin in September and include rock blasting.
Permit applications indicated plans to dig below 15 feet. Phone and email messages were left at one of Waisbrod’s Brooklyn-based businesses.
Engineering drawings submitted with the applications show various plans to brace walls at the edge of the site. Messages were left Thursday for the engineer, Jieming Wang, and for an inspector who’s listed as being involved with the project.
This was the second high-profile structural problem with a building in New York in the past five months. In July, several buildings in Manhattan were evacuated after support columns buckled inside a skyscraper that once was the headquarters of Pfizer.
First responders in Brooklyn worked to clear a massive heap that included mattresses, a broken sink and a refrigerator tossed on its side. Scattered in the debris were vinyl records, clothes and shoes.
Firefighters pulled a pregnant woman from the rubble Wednesday, hoisted her up on a stretcher and rushed her to a waiting ambulance. Others were rescued as the night wore on.
Building records show there were four apartments on the upper two floors and a commercial unit on the ground floor of the collapsed building.
Among those killed and injured were people from Mexico, Colombia, Ecuador and Trinidad, New York’s mayor said. Two of the dead were construction workers, Mamdani said.
Some workers who survived joined firefighters in digging out survivors, he said.
The Consulate of Ecuador in New York said José Luis Caguana Cosquillo and Gabriel Ariolfo Siguencia Yupa, both from Ecuador, were among those killed.